ACCA考试科目一共有15门,其中F2为《管理会计》,这门科目的主要内容是关于管理会计体系的主要元素和管理会计的作用,其中涉及较多的知识点多且杂,如管理会计,管理信息,成本会计等,考试难点较多,F2《管理会计》重点难点资料,具体如下:

重点关注!ACCA考试科目F2重难点资料!

  1.Target cost=target selling price–target profit=market price–desired profit margin.

  2.cost gap=estimated cost–target cost.

  3.TQM:

  ①preventing costs

  ②appraisal costs

  ③internal failure costs

  ④external failure cost

  4.Alternative costing principle:

  ①ABC(activity based costing)

  ②Target costing

  ③Life cycle

  ④TQM

  8.Time series:

  ①trend

  ②seasonal variation:⑴加法模型sum to zero;⑵乘法模型sum to 4

  ③cyclical variation

  ④random variation

  9.pricipal budget factor关键预算因子:be limited the activities

  10.budget purpose:

  ①communication

  ②coordination

  ③compel the plan

  ④motivative employees

  ⑤resource allocation

  11.Budget committee的功能:①coordinated②administration

  12.Budget:①function budget②master budget:1.P&L;2.B/S;3.Cash Flow

  13.Fixed Budget:不是在于固不固定,而是基于一个业务量的考虑,financail expression.

  Flexible Budget:包含了固定成本和变动成本,并且变动成本的变化是随着业务量的变化而改变。

  14.Flexible Budget的优点:

  ①recognize different cost behavior.

  ②improve quality and a comparison of like with like

  ③help managers to forecast cost,revenue and profit.

  15.Flexible Budget的缺点:

  ①假设太简单。

  ②需要更多的时间准备预算编制。

  16.Controllable cost is a“cost which can be influenced by”its budget holder.大部分的变动成本是可控的,non-controllable cost为inflation.

  17.Budget Behavior:

  ①participate approach

  ②imposed budget

  18.payback投资回收期的缺点:

  ①ignore profitability

  ②the time value of money is ignored

  ③没有考虑项目后期带来的经济利益

  ④arbitray武断

  19.payback投资回收期的优点:

  ①easy to calculate

  ②widely use

  ③minimize the effect of the risk and help liqidity

  ★如果在算投资回收期的时候,发生折旧,则需要加回折旧,因为折旧是非现金项目。

  20.(1+real interst rate)*(1+inflation rate)=(1+nominal interest rate)

  21.NPV=present value of future net cash flow–present value of initial cost

  22.永续年金=A/i

  23.每年的汇报是相同的就查看年金现值系数表,不同的就查看年金系数表。

  24.EAR=CAR=APR=(1+r/n)n–1有效年利率

  25.IRR:(based on cash flow analysis)

  ①IRR>cost of capital,NPV>0,worth taking

  ②IRR<cost of capital,NPV<0,not worthwhile.

  26.ARR=average profit/average investment(ARR是基于profit)

  Average investment=(initial investment–residual value)/2

  27.type of standard:

  ①basic standard

  ②current standard

  ③ideal standard

  ④attainable standard

  28.Variance

  ⅠMaterial Variance

  ⑴total material variance=standard cost–actual cost

  ⑵material price variance=(standard price–actual price)*actual quantity

  ⑶material usage variance=(standard usage of actual output-actual usage)*standard price.

  ⅡDirect Labor Variance

  ⑴standard pay–actual pay

  ⑵Labor rate variances=(standard rate–actual rate)*actual hrs of actual output

  ⑶Labor efficiency variances=(standard hrs of actual output–actual hrs)*standard rate

  ⅢVariable production overhead variances

  ⑴Total variable O.H.variance=standard cost–actual cost

  ⑵Variable O.H.expenditure variance=(standard rate–actual rate)*actual hrs

  ⑶Variable O.H.efficiency variance=(standard hrs of actual output–actual hrs)*standard rate

  ⅣFixed O.H.expenditure variance

  ⑴Fixed O.H.Expenditure variance=budget expenditure–actual expenditure

  ⑵Fixed O.H.volume=(actual output-budgeted volume)*standard hrs per unit*standard rate per hr.

  ⑶Capacity variance=(actual hrs worked–budgeted hrs worked)*standard rate per hr

  ⑷Efficiency variance=(standard hrs worked for actual output–actual hrs worked)*standard rate per hr⑴+⑵:Fixed O.H.total variance=fixed O.H.absorbed–actual expenditure

  ⅤSales variance

  ⑴Sales price variances=(actual price–budget price)*actual sales units

  ⑵Sales volume variances=(actual sales units–budget sales units)*standard profit per unit

  (absorption)

  ⑶Sales volume variances=(actual sales units–budget sales units)*standard CPU(marginal costing)

  ⅥIdle time variances

  Idle time variance=(expected idle time–actual idle time)*adjusted hr rate

  29.The elements of a mission statement including:

  ①Purpose

  ②Strategy

  ③Policies and standards of behavior

  ④Values and culture

  30.A critical success factor is a performance requirement that is fundamental to competitive success.

  31.Profitability ratios

  ①Return on capital employed(ROCE)

  =profit before interest and tax/(shareholders’funds+long-term liabilities)×100%

  ②Return on equity(ROE)=profit after tax/shareholders’funds×100%

  ③Asset turnover=sales/capital employed×100%

  =sales/(shareholders’funds+long-term liabilities)×100%

  ④Profit margin=profit before interest and tax/sales×100%

  Profit margin×asset turnover=ROCE

  32.Debt and gearing ratios

  ①Debt-to-equity ratio=long-term liabilities/total equity×100%

  ②Interest cover=PBIT/Interest×100%

  33.Liquidity ratios

  ①Current ratio=current assets/current liabilities

  ②Quick ratio(acid test ratio)=current assets minus inventory/current liabilities

  34.Working capital ratios

  ①Inventory days=average inventory*365/cost of sales

  ②Receivables days=average trade receivables*365/sales

  ③Payables days=average trade payables*365/cost of sales(or purchases)

  35.Non-financial performance measures

  Non-financial performance measures are considered to be leading indicators of financial performance.

  ①Market share

  ②Innovation

  ③Growth

  ④Productivity

  ⑤Quality

  ⑥Social aspects

  36.The balanced scorecard:

  ①financial perspective

  ②external perspective

  ③customer perspective

  ④learning and innovation perspective

  37.Benchmarking:

  ①Internal benchmarking

  ②Competitive benchmarking

  ③Functional benchmarking

  ④Strategic benchmarking

  38.Value analysis is a planned,scientific approach to cost reduction,which reviews the material composition of a product and the product's design so that modifications and improvements can be made which do not reduce the value of the product to the customer or user.

  39.Four aspects of'value'should be considered:

  ①Cost value

  ②Exchange value

  ③Utility value

  ④Esteem value

  40.ROI=PBIT/capital employed*100%

  Widely used and accepted;As a relative measure it enables comparisons to be made with divisions or companies of different sizes.

  41.RI=PBIT-Imputed interest*capital employed.

  Possible to use different rates of interest for different types of assets;Cost of finance is being considered.